After the initial six weeks, the Abuja airport runway will still require
another 18 weeks of ‘upgrade,’ an official said on Sunday.
According to a statement circulated to select journalists by the
presidency, the 18 weeks’ upgrade would however, be carried out at
night, meaning normal flight operations will continue during the day.
The source also said the Minister of State for Aviation, Hadi Sirika,
has been working diligently to minimise the inconvenience caused by the
closure.
“After the Abuja airport reopens for operations on April 19, upgrade
works on the runway would continue for another 18 weeks,” he said.
“This second phase of upgrade works on the runway will be carried out at
night, with no disruption to flight schedules, the Presidency official
further disclosed.”
The source added that a media tour to allow reporters observe and assess
the progress of work on the Abuja airport runway repairs would hold
this week.
He added that “the repair is about its mid-point on Wednesday’’.
The committee had launched series of customer engagement initiatives to
enable passengers and travellers affected by the closure of the Abuja
airport get up-to-date information and updates.
These include a Call Centre (open 7a.m to 10 p.m. Mondays to Fridays and
10 a.m. to 4 p.m. Saturdays and Sundays), a website
(AbujaAirportClosure.info), and a Twitter handle (@ABVClosure).
The closure of the Abuja airport and subsequent use of the Kaduna
airport has faced heavy criticism even as most foreign airlines stayed
away rather than use the Kaduna airport.
Last week, the House of Representativescondemned the arrangements made at the Kaduna airport saying the airport was unsafe and insecure,
On Sunday, the presidency source also said the Federal Government
Coordinating Committee overseeing the repairs of Abuja airport said over
43,000 passengers have passed through the Kaduna airport.
The committee which also oversees the closure and relocation of
passengers to Kaduna airport, the alternative to the Abuja airport, said
that the figure was in respect of the first 11 days of operations in
the exercise.
The committee disclosed this in its latest data submitted to the
presidency on the Abuja airport’s repair, closure and relocation.
The presidential aide, who preferred not to be named, said the figure
was more than the 41,000 passengers the Kaduna airport recorded in the
entire first quarter of 2015, and the 21,000 in the first quarter of
2016.
The source also disclosed that, during this period, about 10,000
passengers took advantage of the free bus shuttle, organised by the
federal government to transport passengers between the Abuja and Kaduna
airports.
“The free bus shuttle conveyed passengers between Abuja and Kaduna
airports, starting at the Abuja airport at 6 o’clock in the morning, and
at the Kaduna Airport from 8 a.m.
“The shuttle takes 3 hours from airport to airport, and runs every 30
minutes, until the arrival of the last daily flight in Kaduna.
“The Shuttle is in addition to the federal government’s free train service between Abuja and Kaduna.
“The two-and-half-hour Train Service departs Abuja’s Idu Station for
Kaduna at 6 a.m., 11.55 a.m. and 5.45 p.m. Mondays to Saturdays; and
departs Kaduna’s Rigasa Station for Abuja at 9 a.m., 2.50 p.m. and 8.40
p.m.,’’ the source said.
According to the source, the reconstruction at the Abuja airport is
going according to schedule. He expressed optimism that the airport will
reopen after six weeks as planned.
The official is also involved in the presidential supervision of the airport closure and oversight.